File #: BILL NO. 17-32    Name:
Type: Ordinance Status: Passed
File created: 1/17/2017 In control: City Council - Regular Session
On agenda: 2/9/2017 Final action: 2/9/2017
Title: AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND WALTER P. MOORE, IN AN AMOUNT NOT TO EXCEED $150,110.00 FOR ENGINEERING SERVICES FOR THE COMMERCE DRIVE IMPROVEMENTS (RFQ NO. 2017-305B). (PWC 1/30/17)
Attachments: 1. Ordinance, 2. Agreement, 3. Commerce Map
Related files: BILL NO. 18-165, BILL NO. 20-28

Title

AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND WALTER P. MOORE, IN AN AMOUNT NOT TO EXCEED $150,110.00 FOR ENGINEERING SERVICES FOR THE COMMERCE DRIVE IMPROVEMENTS (RFQ NO. 2017-305B). (PWC 1/30/17)

 

 

Body

Issue/Request:

AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND WALTER P. MOORE, IN AN AMOUNT NOT TO EXCEED $150,110.00 FOR ENGINEERING SERVICES FOR THE COMMERCE DRIVE IMPROVEMENTS (RFQ NO. 2017-305B).

 

Key Issues:

•   The NW Commerce Drive project was authorized by Council in February 2016 and then formally approved in June 2016 as part of FY 2017 Capital Improvement Plan (CIP)

 

•   The project will be funded using cost savings from the voter-approved 2007 CIP Sales Tax

 

•   City Staff Issue RFQ No. 2017-305 to conduct a Qualification Based Selection for professional engineering services, in accordance with state statutes and local procurement policies

 

•   Walter P. Moore, Inc. was selected for the project and satisfactorily conducted negotiations for scope and fee with City Staff

 

 

Proposed City Council Motion:

FIRST MOTION:  I move for a second reading of AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND WALTER P. MOORE, IN AN AMOUNT NOT TO EXCEED $150,110.00 FOR ENGINEERING SERVICES FOR THE COMMERCE DRIVE IMPROVEMENTS (RFQ NO. 2017-305B).

 

SECOND MOTION:  I move for adoption of AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND WALTER P. MOORE, IN AN AMOUNT NOT TO EXCEED $150,110.00 FOR ENGINEERING SERVICES FOR THE COMMERCE DRIVE IMPROVEMENTS (RFQ NO. 2017-305B).

 

Background:

In February 2016, City Council approved the construction of Commerce Drive using the savings from the CIP Sales Tax Renewal fund.    The work will construct approximately 800 feet of Commerce Drive from Main Street to Tudor Road as shown in the City’s 2006 and 2016 Thoroughfare Master Plan documents.  The preliminary budget for the project of $1,231,000 was authorized when the FY 2017 CIP was recommended for approval by the Planning Commission and then adopted by Council Resolution. 

 

The primary reasons for this project are to improve economic development opportunities in the area and improve traffic safety.  The project will build a dead end cul-de-sac near the intersection of Main Street and Tudor Road, and extend Commerce Drive to intersect Tudor Road in line with NW Sloan Street.  This realignment will eliminate poor sight distance where Main currently crosses Tudor Road near the east end of the bridge over the railroad tracks.  The project will also include water main relocation and sanitary sewer extension.  These two utility improvements, couple with the road, will improve access to land that is zoned for commercial/industrial use, and improve access to land currently owned by the City.  Design and right of way acquisition will occur in 2017.  Pending successful right of way acquisition, the project would be built in 2018.

 

Impact/Analysis:

This is the City's standard agreement between the City and a consulting engineering firm with regard to engineering services.  This agreement will allow Walter P. Moore to provide engineering services to the City.

 

Timeline:

Start: Spring 2017

Finish: Fall 2018

 

Other Information/Unique Characteristics:

RFQ No. 2017-305 was publicly advertised starting October 20, 2016.  The RFQ combined 3 small projects, NW Commerce Drive, NE Gateway Drive and SE 5th Terrace in the submittal.  The RFQ was advertised using the City’s web site and www.PublicPurchase.com to notify potential vendors.  At least 39 potential vendors viewed the RFQ, and 12 firms submitted responsive qualification submittals by the November 14, 2016 closing date.  Based on the relatively small size and scope of the work, firms were selected based on submittals and no interviews were conducted.  From that list of 12, three firms were selected, with a firm assigned to each project.  Walter P. Moore Inc. was selected for NW Commerce Drive, Garver  LLC was selected for NE Gateway, and Allgeier, Martin and Associates Inc. was selected for SE 5th Terrace.

 

Presenter

Presenter: Karen Quackenbush, Staff Engineer

 

Recommendation

Recommendation:  Staff recommends approval of AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND WALTER P. MOORE, IN AN AMOUNT NOT TO EXCEED $150,110.00 FOR ENGINEERING SERVICES FOR THE COMMERCE DRIVE IMPROVEMENTS (RFQ NO. 2017-305B).

 

 

Committee Recommendation

Committee Recommendation: The Public Works Committee voted unanimously 3-0 to recommend to City Council approval of AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND WALTER P. MOORE, IN AN AMOUNT NOT TO EXCEED $150,110.00 FOR ENGINEERING SERVICES FOR THE COMMERCE DRIVE IMPROVEMENTS (RFQ NO. 2017-305B).