File #: BILL NO. 23-046    Name:
Type: Ordinance - Committee Status: Passed
File created: 1/25/2023 In control: City Council - Regular Session
On agenda: 2/28/2023 Final action: 2/28/2023
Title: An Ordinance approving Change Order No. 4 to the Agreement for the construction of Water Main Replacement: FY21 Project, Project No. 438-1, between the City of Lee's Summit, Missouri, and Wiedenmann, Inc. for an increase of $88,332.93 for a revised agreement amount of $4,096,487.30 and authorizing the City Manager to execute the same. (PWC 2/13/23)
Sponsors: Public Works Admin & Engineering
Attachments: 1. Ordinance, 2. Attachment: Change Order 4
Related files: BILL NO. 22-210, BILL NO. 22-35, BILL NO. 21-81
Title
An Ordinance approving Change Order No. 4 to the Agreement for the construction of Water Main Replacement: FY21 Project, Project No. 438-1, between the City of Lee's Summit, Missouri, and Wiedenmann, Inc. for an increase of $88,332.93 for a revised agreement amount of $4,096,487.30 and authorizing the City Manager to execute the same. (PWC 2/13/23)

Body
Issue/Request:
An Ordinance approving Change Order No. 4 to the Agreement for the construction of Water Main Replacement: FY21 Project, Project No. 438-1, between the City of Lee's Summit, Missouri, and Wiedenmann, Inc. for an increase of $88,332.93 for a revised agreement amount of $4,096,487.30 and authorizing the City Manager to execute the same.

Key Issues:

· Pursuant to Ordinance No. 9132, the City and Wiedenmann, Inc., (hereinafter "Contractor") entered into an Agreement for the construction of the Water Main Replacement: FY21 Project, Project No. 438-1, (hereinafter "Base Agreement").

· The City and Contractor modified the Base Agreement, as amended, per Change Order No. 1 for increased costs and timeline associated with an emergency water break repair.

· Pursuant to Ordinance No. 9346, the City and Contractor further modified the Base Agreement, as amended, per Change Order No. 2 for increased costs associated with the relocation of several water meters at an apartment complex and unavoidable curb, driveway and sidewalk restoration during the pipe bursting process.

· Pursuant to Ordinance No. 9524, the City and Contractor further modified the Base Agreement, as amended, per Change Order No. 3 for increased costs associated with the relocation of several water meters at an apartment complex and unavoidable curb, driveway and sidewalk restoration during the pipe bursting process.

· The City desires to further modify the Base Agreement, as amended, for increased costs associated with upsizing portions of the existing main, trench excavation due to electric conflicts, additional shoring and ex...

Click here for full text