File #: BILL NO. 17-56    Name:
Type: Ordinance Status: Passed
File created: 12/27/2016 In control: City Council - Regular Session
On agenda: 3/9/2017 Final action: 3/9/2017
Title: AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND GEORGE BUTLER ASSOCIATES, INC. IN THE AMOUNT OF $272,114.00 FOR PROFESSIONAL ENGINEERING SERVICES FOR SW JEFFERSON ST (PERSELS RD TO OLDHAM PKWY) (RFQ NO. 419-32272). (PWC 2-23-17)
Sponsors: Public Works
Attachments: 1. Ordinance, 2. Agreement, 3. Ranking Sheet, 4. Location map
Related files: BILL NO. 19-283, BILL NO. 17-246, BILL NO. 20-105, BILL NO. 18-184

Title

AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND GEORGE BUTLER ASSOCIATES, INC. IN THE AMOUNT OF $272,114.00 FOR PROFESSIONAL ENGINEERING SERVICES FOR SW JEFFERSON ST (PERSELS RD TO OLDHAM PKWY) (RFQ NO. 419-32272). (PWC 2-23-17)

Body

Issue/Request:

AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND GEORGE BUTLER ASSOCIATES, INC. IN THE AMOUNT OF $272,114.00 FOR PROFESSIONAL ENGINEERING SERVICES FOR SW JEFFERSON ST (PERSELS RD TO OLDHAM PKWY) (RFQ NO. 419-32272).

Key Issues:
- The SW Jefferson Street project from Persels to Oldham was authorized by Council in February 2016 and then formally approved in June 2016 as part of FY 2017 Capital Improvement Plan (CIP)

- The project will be funded using cost savings from the voter-approved 2007 CIP Sales Tax Renewal

- City Staff Issue RFQ No. 419-32272 to conduct a Qualification Based Selection for professional

engineering services, in accordance with state statutes and local procurement Policies

- George Butler Associates, Inc. was selected for the project and satisfactorily conducted negotiations for scope and fee with City Staff

 

Proposed City Council Motion:

FIRST MOTION:  I move for a second reading of AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND GEORGE BUTLER ASSOCIATES, INC. IN THE AMOUNT OF $272,114.00 FOR PROFESSIONAL ENGINEERING SERVICES FOR SW JEFFERSON ST (PERSELS RD TO OLDHAM PKWY) (RFQ NO. 419-32272).

 

SECOND MOTION:  I move for adoption of AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND GEORGE BUTLER ASSOCIATES, INC. IN THE AMOUNT OF $272,114.00 FOR PROFESSIONAL ENGINEERING SERVICES FOR SW JEFFERSON ST (PERSELS RD TO OLDHAM PKWY) (RFQ NO. 419-32272).

 

Background:

The project will promote economic development in the area and improve capacity.  The project will be built in coordination with the MoDOT improvements to US 50 and M291 South interchange project, and proposed development work along the M291 corridor.  The improvements will match the Jefferson Street improvement south of Persels, that include building a 3-lane road, sidewalk, multi-use path, curb and gutter, enclosed storm drain, street lighting, and utility relocations.  This project is funded by the CIP sales tax renewal, with water and sewer relocates funded by Water Utilities.  This work was coordinated with the 291 corridor master planning study and downtown trail connection project.

 

Public Works issued RFQ 419-32272. The RFQ was advertised in the City website and www.PublicPurchase.com. Engineering firms were notified by Public Purchase for access to the documents and 15 firms were notified by email. Ten firms submitted statements of qualifications prior to the November 22, 2016 closing date. All submittals were evaluated by a City Staff evaluation team composed of five personnel with representatives from Public Works.

Impact/Analysis:

 

Timeline:

Estimated Start:                      March 2017

Estimated Finish:                     February 2018

 

Other Information/Unique Characteristics:

[Enter text here]

 

Presenter
Presenter:  Mark Green, Staff Engineer

 

Recommendation

Staff Recommendation:  Staff recommends approval of AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND GEORGE BUTLER ASSOCIATES, INC. IN THE AMOUNT OF $272,114.00 FOR PROFESSIONAL ENGINEERING SERVICES FOR SW JEFFERSON ST (PERSELS RD TO OLDHAM PKWY) (RFQ NO. 419-32272).

 

Committee Recommendation:  The Public Works Committee voted unanimously 4-0 to recommend to City Council approval of AN ORDINANCE AUTHORIZING THE EXECUTION OF AN AGREEMENT BY AND BETWEEN THE CITY OF LEE'S SUMMIT, MISSOURI, AND GEORGE BUTLER ASSOCIATES, INC. IN THE AMOUNT OF $272,114.00 FOR PROFESSIONAL ENGINEERING SERVICES FOR SW JEFFERSON ST (PERSELS RD TO OLDHAM PKWY) (RFQ NO. 419-32272).