File #: 2024-6153    Name:
Type: Public Hearing - Legislative Status: Presented
File created: 2/23/2024 In control: Land Clearance for Redevelopment Authority
On agenda: 2/28/2024 Final action: 3/26/2024
Title: Public Hearing - Bayberry Crossing Land Clearing for Redevelopment Authority (LCRA) Redevelopment Plan
Attachments: 1. Exhibit List, 2. LCRA Process Outline, 3. Developer Slides, 4. City Slides, 5. LCRA Redevelopment Plan, 6. LCRA Resolution 2024-1, 7. Financial Incentive Pre-Application Worksheet & Developer Modeling, 8. Ordinance 7472 (Hwys 50 & 291 Urban Renewal Area), 9. LCRA Lease Protections
Related files: 2023-5980, 2024-6154, 2024-6167
Title
Public Hearing - Bayberry Crossing Land Clearing for Redevelopment Authority (LCRA) Redevelopment Plan

Body
Issue/Request:
Public Hearing - Bayberry Crossing LCRA Redevelopment Plan

Key Issues:
Request for a CID and LCRA redevelopment plan to provide reimbursement to Developer for certain qualified redevelopment costs associated with the shopping center improvement work. Developer’s proposed reimbursable costs include these shopping center renovation costs:

- Main Center Facades and Building Envelope Integrity
- Landscaping (including irrigation)
- Signage
- LED lighting
- Amenities (benches, planters, etc.)

The LCRA redevelopment plan would be in place for the redevelopment time period only, to provide sales tax exemption on construction materials that are used in the renovation process. The property would return to the tax rolls after the redevelopment work is completed. The applicant is not seeking a property tax abatement.

Background:
A Conceptual Economic Development Incentive Request was presented to the City Council at the January 9, 2024 City Council meeting.

Baceline, LLC ("Developer"), is proposing to undertake remodeling, updates and improvements to the Bayberry Crossing shopping center. The shopping center parcel is about 5.05 acres and the building size of the completed project is about 54,000 square feet.

The Developer proposes to use a community improvement district (CID) which would impose a 1% sales tax for up to 27 years, which the maximum duration allows by the CID Act. Developer projects that the sales tax revenues in the first year of the CID will be about $75,000/year, which represents $7.5 million in annual taxable sales, and would accelerate to about $10 million in annual taxable sales after 6 years. Developer projects that the total net present value of the reimbursement will be about $1.5 million after 27 years.

Developer also requests the use of an LCRA redevelopment plan to provide sales tax exemption on constr...