File #: BILL NO. 24-032    Name:
Type: Ordinance - Committee Status: Passed
File created: 1/17/2024 In control: City Council - Regular Session
On agenda: 2/12/2024 Final action: 2/27/2024
Title: An Ordinance approving Change Order No. 1 to the agreement with Pavement Management, LLC for the Crack Seal FY24 Program, Project No. 815 to increase the project timeline by 18 days, and authorizing the City Manager to execute an agreement for the same. (PWC 2/12/24)
Sponsors: Public Works Admin & Engineering
Attachments: 1. Ordinance, 2. Attachment: Change Order No. 1
Related files: BILL NO. 23-165
Title
An Ordinance approving Change Order No. 1 to the agreement with Pavement Management, LLC for the Crack Seal FY24 Program, Project No. 815 to increase the project timeline by 18 days, and authorizing the City Manager to execute an agreement for the same. (PWC 2/12/24)
Body
Issue/Request:
An Ordinance approving Change Order No. 1 to the agreement with Pavement Management, LLC for the Crack Seal FY24 Program, Project No. 815 to increase the project timeline by 18 days, and authorizing the City Manager to execute an agreement for the same.

Key Issues:

· Pursuant to Ordinance No. 9735, the City entered into a contract with Pavement Management, LLC. to complete the FY24 Crack Seal Program

· During the 60-day agreement, the number of days deemed too wet to install the crack seal equaled 18 more days than normally expected.

· The City desires to add 18 days in agreement with Pavement Management, LLC to Project No. 815 for a 30% increase of the original contract time.

· Section 8.2.3 of the City’s Procurement Policy states that the City Council must approve any change order resulting in an increase to the contract time exceeding the greater of 30 days or twenty percent (20%) of the original contract time.

Proposed Committee Motion:
I move to recommend to the City Council approval of an Ordinance approving Change Order No. 1 to the agreement with Pavement Management, LLC for the Crack Seal FY24 Program, Project No. 815 to increase the project timeline by 18 days, and authorizing the City Manager to execute an agreement for the same.

Proposed Council Motion:
FIRST MOTION: I move for a second reading of an Ordinance approving Change Order No. 1 to the agreement with Pavement Management, LLC for the Crack Seal FY24 Program, Project No. 815 to increase the project timeline by 18 days, and authorizing the City Manager to execute an agreement for the same.

SECOND MOTION: I move for adoption of an Ordinance approving Change Order No. 1 to the agreement with Pa...

Click here for full text