File #: BILL NO. 21-44    Name:
Type: Ordinance Status: Passed
File created: 2/21/2021 In control: City Council - Regular Session
On agenda: 3/9/2021 Final action: 3/9/2021
Title: An Ordinance approving Change Order No. 1 to the contract with MegaKC Corporation for the Jefferson Street Improvements project, an increase of 128 calendar days to reach substantial completion for a revised substantial completion date of May 25, 2021. (PWC 3/1/21)
Sponsors: Public Works Admin & Engineering
Attachments: 1. Ordinance, 2. Change Order 1, 3. Weighted Time Table - No Winter Shutdown
Related files: BILL NO. 20-105, BILL NO. 21-148
Title
An Ordinance approving Change Order No. 1 to the contract with MegaKC Corporation for the Jefferson Street Improvements project, an increase of 128 calendar days to reach substantial completion for a revised substantial completion date of May 25, 2021. (PWC 3/1/21)

Body
Issue/Request:
An Ordinance approving Change Order No. 1 to the contract with MegaKC Corporation for the Jefferson Street Improvements project, an increase of 128 calendar days to reach substantial completion for a revised substantial completion date of May 25, 2021.

Key Issues:
· Delayed Notice to Proceed pushed the end of the project into the winter, requiring more time to be added to the contract
· Ongoing utility conflicts and change order items affected anticipated construction production rates
· Abnormal weather conditions significantly reduced the time available to work on the project
· The City’s procurement policy requires Council approval for adding more than 30 days and/or adding time that exceed 10 % of the original contract time


Proposed City Council Motion:
FIRST MOTION: I move for second reading of an Ordinance approving Change Order No. 1 to the contract with MegaKC Corporation for the Jefferson Street Improvements project, an increase of 128 calendar days to reach substantial completion for a revised substantial completion date of May 25, 2021.
SECOND MOTION: I move for adoption of an Ordinance approving Change Order No. 1 to the contract with MegaKC Corporation for the Jefferson Street Improvements project, an increase of 128 calendar days to reach substantial completion for a revised substantial completion date of May 25, 2021

Background:
This Change Order addresses all issues related to time thru February 21, 2021. These issues include the following:

1. Delayed Notice to Proceed: The contractor intended to start the project on July 27, 2020. This would have set the Substantial Completion Date (SCD) at December 12, 2020. Using MoDOT’s weighted timetable for project...

Click here for full text