File #: BILL NO. 20-31    Name:
Type: Ordinance Status: Passed
File created: 1/21/2020 In control: City Council - Regular Session
On agenda: 2/18/2020 Final action: 2/18/2020
Title: An Ordinance approving Change Order No. 3 to the contract with Westland Construction, Inc. for the FY19 watermain replacement project, an increase of $19,601.68 for a revised contract price of $1,318,958.23 and an increase of 73 calendar days to reach substantial and final completion. (PWC 2/03/20)
Attachments: 1. Ordinance, 2. Change Order 3
Related files: BILL NO. 20-246
Title
An Ordinance approving Change Order No. 3 to the contract with Westland Construction, Inc. for the FY19 watermain replacement project, an increase of $19,601.68 for a revised contract price of $1,318,958.23 and an increase of 73 calendar days to reach substantial and final completion. (PWC 2/03/20)

Body
Issue/Request:
An Ordinance approving Change Order No. 3 to the contract with Westland Construction, Inc. for the FY19 watermain replacement project, an increase of $19,601.68 for a revised contract price of $1,318,958.23 and an increase of 73 calendar days to reach substantial and final completion.

Key Issues:
? A section of watermain replacement was added near the intersection of Chipman and Ward, requiring 17 additional days to complete this work.
? The scope of work changed at two separate locations along Woods Chapel Road, resulting in an additional 30 days to complete the work.
? 5 calendar days are being added to the raintree drive area as a result of ductile iron pipe being encountered in lieu of cast iron pipe as indicated in the plans.
? SW Seagull Street was added to the contract. 21 days are being added to complete this work.
? Additional quantities are being added for the SW Seagull Street watermain replacement.

Proposed City Council Motion:
FIRST MOTION: I move for a second reading of an Ordinance approving Change Order No. 3 to the contract with Westland Construction, Inc. for the FY19 watermain replacement project, an increase of $19,601.68 for a revised contract price of $1,318,958.23 and an increase of 73 calendar days to reach substantial and final completion.
SECOND MOTION: I move for adoption of an Ordinance approving Change Order No. 3 to the contract with Westland Construction, Inc. for the FY19 watermain replacement project, an increase of $19,601.68 for a revised contract price of $1,318,958.23 and an increase of 73 calendar...