File #: BILL NO. 19-257    Name:
Type: Ordinance Status: Passed
File created: 10/30/2019 In control: City Council - Regular Session
On agenda: 11/19/2019 Final action: 11/19/2019
Title: An Ordinance approving the award of Bid No. 2020-034 for Fire Station # 6 roof replacement to Greenriver Roofing and Construction, Inc. and authorizing the City Manager to enter into and execute agreement for the same by and on behalf of the City of Lee’s Summit, Missouri. (F&BC 11/11/19)
Attachments: 1. Ordinance, 2. Fire #6 2020-034 Bid Tab, 3. 2020-034 Contract Agreement, 4. Green River Roofing and Construction Inc. Bid Proposal
Title
An Ordinance approving the award of Bid No. 2020-034 for Fire Station # 6 roof replacement to Greenriver Roofing and Construction, Inc. and authorizing the City Manager to enter into and execute agreement for the same by and on behalf of the City of Lee’s Summit, Missouri. (F&BC 11/11/19)

Body
Issue/Request:
An Ordinance approving the award of Bid No. 2020-034 for Fire Station # 6 roof replacement to Greenriver Roofing and Construction, Inc. and authorizing the City Manager to enter into and execute agreement for the same by and on behalf of the City of Lee’s Summit, Missouri.

Background:
The current roof on Fire Station #6 is over 21 years old and has a great deal of deterioration. The roof is now due for replacement. The new roof replacement project cost is $55,097.01 and therefore requires City Council approval before it can proceed. This will be a BERP funded project.

Key Issues:
The Procurement and Contract Services Division formally solicited Bid No. 2020-034 for FIre Station # 6 roof replacement via its' e-bidding service Public Purchase.

One hundred and twenty nine (129) potential bidders were notified via the City's e-bidding service, Public Purchase. The advertisement for the formal bid was also posted on the City's website. Public Purchase Report Records show that fourty one (41) potential firms accessed the online bid document 2020-034.

Upon the bid opening date of October 25, 2019, the Procurement and Contract Services Division received four (4) bids. The Project Manager from Central Building Services Division evaluated the bids received and the attached bid tabulation. Based on the critical need for such service, the Project Manager deemed it necessary to recommend the lowest and most responsive bidder, which was Greenriver Roofing and Construction Inc.

If awarded, the bid tabulation amounts identified shall lock in unit prices identified for both labor and material for the roof replacement project.

Proposed Council Mot...