File #: BILL NO. 19-201    Name:
Type: Ordinance Status: Passed
File created: 8/13/2019 In control: City Council - Regular Session
On agenda: 9/3/2019 Final action: 9/3/2019
Title: An Ordinance approving Change Order No. 1 to the contract with Beemer Construction Company, Inc. for the Winterset Woods & Sterling Hills Trunk Sewer Main project, an increase of 81 calendar days to reach Substantial and Final Completion for a revised Substantial Completion Date of September 28, 2019, and authorizing the City Manager to execute the same by and on behalf of the City. (PWC 8/27/19)
Sponsors: Public Works Admin & Engineering
Attachments: 1. Ordinance, 2. Change Order
Related files: BILL NO. 18-145, BILL NO. 20-51

Title

An Ordinance approving Change Order  No. 1 to the contract with Beemer Construction Company, Inc. for the Winterset Woods & Sterling Hills Trunk Sewer Main project, an increase of 81 calendar days to reach Substantial and Final Completion for a revised Substantial Completion Date of September 28, 2019, and authorizing the City Manager to execute the same by and on behalf of the City. (PWC 8/27/19)

 

Body

Issue/Request:

An Ordinance approving Change Order  No. 1 to the contract with Beemer Construction Company, Inc. for the Winterset Woods & Sterling Hills Trunk Sewer Main project, an increase of 81 calendar days to reach Substantial and Final Completion for a revised Substantial Completion Date of September 28, 2019, and authorizing the City Manager to execute the same by and on behalf of the City.

 

Key Issues:

                      Abnormally wet weather conditions limited access to the project

                     MoDOT’s Weighted Timetable was used to quantify the impact the wet weather had on the project schedule

                     The Contractor should be allowed additional time to complete the work based on weather and the MoDOT calculation method

 

 

Proposed City Council Motion:

FIRST MOTION: I move for a second reading of an Ordinance approving Change Order  No. 1 to the contract with Beemer Construction Company, Inc. for the Winterset Woods & Sterling Hills Trunk Sewer Main project, an increase of 81 calendar days to reach Substantial and Final Completion for a revised Substantial Completion Date of September 28, 2019, and authorizing the City Manager to execute the same by and on behalf of the City.

SECOND MOTION: I move for adoption of an Ordinance approving Change Order  No. 1 to the contract with Beemer Construction Company, Inc. for the Winterset Woods & Sterling Hills Trunk Sewer Main project, an increase of 81 calendar days to reach Substantial and Final Completion for a revised Substantial Completion Date of September 28, 2019, and authorizing the City Manager to execute the same by and on behalf of the City.

 

Background:

The contract documents allow for an adjustment in calendar days to complete the project in the event of abnormal weather conditions.  Based on historical data, staff agreed abnormally wet conditions existed between the Notice to Proceed Date and May 28, 2019. In an effort to fairly quantify the effect the wet weather had on the project schedule, MoDOT’s Weighted Timetable for Contracts with No Time Exclusions was used to determine a revised Substantial Completion Date.

 

 

Impact/Analysis:

[Enter text here]

 

Timeline:

Start: ___

Finish: ___

 

Other Information/Unique Characteristics:

Section 6.4 the City’s Procurement Policy governing changes in contract time states the following:

                     “Change orders resulting in a revised contract time exceeding ten percent (10%) of the original contract time, a single change order increasing contract time by 30 days or more… must be approved by the City Council.”

 

Presenter

Dena Mezger, Director of Public Works

Recommendation

Recommendation: Staff recommends approval of an Ordinance approving Change Order  No. 1 to the contract with Beemer Construction Company, Inc. for the Winterset Woods & Sterling Hills Trunk Sewer Main project, an increase of 81 calendar days to reach Substantial and Final Completion for a revised Substantial Completion Date of September 28, 2019, and authorizing the City Manager to execute the same by and on behalf of the City.

 

 

Committee Recommendation

Committee Recommendation: The Public Works Committee voted unanimously 4-0 to recommend to City Council approval of an Ordinance approving Change Order  No. 1 to the contract with Beemer Construction Company, Inc. for the Winterset Woods & Sterling Hills Trunk Sewer Main project, an increase of 81 calendar days to reach Substantial and Final Completion for a revised Substantial Completion Date of September 28, 2019, and authorizing the City Manager to execute the same by and on behalf of the City.