File #: BILL NO. 19-35    Name:
Type: Ordinance Status: Passed
File created: 2/11/2019 In control: City Council - Regular Session
On agenda: 2/19/2019 Final action: 3/5/2019
Title: An Ordinance awarding Bid No. 40252086-1 for the Phase 3 Landfill Gas Collection System Construction to Joe Coleman & Son Environmental Services, Inc. in the amount of $636,731.73 and authorizing the City Manager to enter into an agreement for the same. (First Reading by Council on February 19, 2019. Passed by unanimous vote.)
Attachments: 1. Ordinance, 2. Agreement, 3. Bid Tabulation
Related files: BILL NO. 19-73, BILL NO. 19-74
Title
An Ordinance awarding Bid No. 40252086-1 for the Phase 3 Landfill Gas Collection System Construction to Joe Coleman & Son Environmental Services, Inc. in the amount of $636,731.73 and authorizing the City Manager to enter into an agreement for the same.
(First Reading by Council on February 19, 2019. Passed by unanimous vote.)

Body
Issue/Request:
An Ordinance awarding Bid No. 40252086-1 for the Phase 3 Landfill Gas Collection System Construction to Joe Coleman & Son Environmental Services, Inc. in the amount of $636,731.73 and authorizing the City Manager to enter into an agreement for the same.

Key Issues:

-The Gas Collection System is part of our Missouri Department of Natural Resources (MDNR) permit.

-The system controls landfill gas by collecting gases to burn at the flare, thus reducing greenhouse gas emissions.

-The Gas Collection System must be installed prior to the start of placement of soil for Landfill Closure.

Proposed City Council Motion:
SECOND MOTION: I move for adoption of an Ordinance awarding Bid No. 40252086-1 for the Phase 3 Landfill Gas Collection System Construction to Joe Coleman & Son Environmental Services, Inc. in the amount of $636,731.73 and authorizing the City Manager to enter into an agreement for the same.

Background:
Summit Waste Systems has indicated that they will close the landfill in mid-March, 2019. After the landfill closes, a soil cap will be placed on top of the landfill. Before the cap is placed, the landfill gas management system will need to be expanded into areas of the landfill that do not currently have wells. These are generally the areas that have most recently received waste. Components of the work to be completed include: installing new vertical gas extraction wells and dewatering pumps, control valves, lateral gas pipes to connect the new wells, air and liquid discharge pipe, and connecting all to the existing system in place currently. All work is to be completed in compliance with the MDNR...

Click here for full text