An ordinance authorizing the execution of Modification No. 1 to agreement dated February 5, 2017 (RFQ NO. 2017-305A) for professional Engineering Services for Gateway Drive improvements by and between the City of Lee's Summit, Missouri, and Garver, LLC, for a net increase of $7,822.00 with a revised contract amount not to exceed $128,224.00. (PWC 6-19-18)
Body
Issue/Request:
Approval of an ordinance authorizing the execution of modification No. 1 to agreement dated February 5, 2017 (RFQ NO. 2017-305A) for professional Engineering Services for Gateway Drive improvements by and between the City of Lee's Summit, Missouri, and Garver, LLC, for a net increase of $7,822.00 with a revised contract amount not to exceed $128,224.00.
Key Issues:
The Gateway Drive Improvements Project was approved by City Council in the FY2018 Capital Improvement Plan and it is funded by savings from the 2007 CIP Sales Tax Renewal.
The City desires to modify the base agreement with Garver to provide additional engineering services during construction.
Construction for this project is scheduled to begin construction in June, 2018.
The budget of $850,000.00 is adequate to provide additional funds for the extra services.
Proposed City Council Motion:
First Motion: I move for a second reading of an ordinance authorizing the execution of modification No. 1 to agreement dated February 5, 2017 (RFQ NO. 2017-305A) for professional Engineering Services for Gateway Drive improvements by and between the City of Lee's Summit, Missouri, and Garver, LLC, for a net increase of $7,822.00 with a revised contract amount not to exceed $128,224.00.
Second Motion: I move for adoption of an ordinance authorizing the execution of modification No. 1 to agreement dated February 5, 2017 (RFQ NO. 2017-305A) for professional Engineering Services for Gateway Drive improvements by and between the City of Lee's Summit, Missouri, and Garver, LLC, for a net increase of $7,822.00 with a revised contr...