File #: BILL NO. 17-137    Name:
Type: Ordinance Status: Passed
File created: 6/8/2017 In control: City Council - Regular Session
On agenda: 6/15/2017 Final action: 6/15/2017
Title: AN ORDINANCE APPROVING CHANGE ORDER #1 - WITH PCi ROADS, LLC FOR THE BRIDGE MAINTENANCE FY17 PROJECT, AN INCREASE OF $105,089.40 AND AN ADDITIONAL 43 CALENDAR DAYS FOR A REVISED CONTRACT PRICE OF $448,417.05 AND 103 CALENDAR DAYS TO REACH SUBSTANTIAL COMPLETION.
Attachments: 1. Ordinance, 2. Change Order #1, 3. Change Order #1 Reasons, 4. Change Order #1 Spreadsheet
Title

AN ORDINANCE APPROVING CHANGE ORDER #1 - WITH PCi ROADS, LLC FOR THE BRIDGE MAINTENANCE FY17 PROJECT, AN INCREASE OF $105,089.40 AND AN ADDITIONAL 43 CALENDAR DAYS FOR A REVISED CONTRACT PRICE OF $448,417.05 AND 103 CALENDAR DAYS TO REACH SUBSTANTIAL COMPLETION.

Body

Issue/Request:

AN ORDINANCE APPROVING CHANGE ORDER #1 - WITH PCi ROADS, LLC FOR THE BRIDGE MAINTENANCE FY17 PROJECT, AN INCREASE OF $105,089.40 AND AN ADDITIONAL 43 CALENDAR DAYS FOR A REVISED CONTRACT PRICE OF $448,417.05 AND 103 CALENDAR DAYS TO REACH SUBSTANTIAL COMPLETION

Key Issues:

•                     Removal of the concrete overlay exposed the extent of needed repair.

•                     Excessive quantity caused a reconsideration of the material type being used for the concrete patches.

•                     Extent of work being performed and the change in material type necessitate additional time being added to the contract

Proposed City Council Motion:

FIRST MOTION: I move for a second reading of AN ORDINANCE APPROVING CHANGE ORDER #1 - WITH PCi ROADS, LLC FOR THE BRIDGE MAINTENANCE FY17 PROJECT, AN INCREASE OF $105,089.40 AND AN ADDITIONAL 43 CALENDAR DAYS FOR A REVISED CONTRACT PRICE OF $448,417.05 AND 103 CALENDAR DAYS TO REACH SUBSTANTIAL COMPLETION

SECOND MOTION: I move for adoption of AN ORDINANCE APPROVING CHANGE ORDER #1 - WITH PCi ROADS, LLC FOR THE BRIDGE MAINTENANCE FY17 PROJECT, AN INCREASE OF $105,089.40 AND AN ADDITIONAL 43 CALENDAR DAYS FOR A REVISED CONTRACT PRICE OF $448,417.05 AND 103 CALENDAR DAYS TO REACH SUBSTANTIAL COMPLETION

Background:

In 1991, the existing Main Street Bridge over Second Street received a 2 inch concrete overlay.  In recent years, the concrete overlay began to indicate signs of failure.  For this reason, it was decided to remove the existing 2 inch concrete overlay, repair any damage to the underlying structure and replace the 2 inch concrete overlay.  Based on visual inspections of the underside of the deck, as w...