Annual Airport Budget Presentation to Board of Aeronautic Commissioners

 

Body

Key Issues:

  • CPI Increase of 2% begining January 1, 2018 recommended
  • 2018 Spring Airport construction project - relocation of taxiway Alpha paving begins, includes removal of Open-T Hangars and 1-S-Hangar Building.
    • Continue to evaluate future operational needs of the Airport after improvements are complete (equipment, staff, etc.).
    • Tenant Open House & Tenant Construction Progress Meetings to update customers about upcoming airport construction projects.
    • Continue, and expand, Airport Marketing Program to attract new fuel sales and business to the Airport.
    • Annual Airport open house event.
    • Attend and staff a booth at the NBAA (National Business Aircraft Association) Schedulers & Dispatchers Conference in February 2018.
    • Marketing budget remains close to last year's amount.
    • Remove & Replace Asphalt 15-approach pads of K & J Hangar units, three-year program to perform all 38-units. First year will address the units needing immediate repairs.

Equipment expansion Requests
• Ground Power Unit (GPU)..$42,000
• Additional Tractor-Mowing/Snow Removal..$69,700
• Line Service Office at Hangar 1 yearly rental and installatiion..$12,950
• Correct Drainage & Safety Issue at Hangar 1.....$23,610
• LED Light conversion at Hangar 1....$22,000
• Auto Gate Opener Hangar 1......$15,155

Personnel expansion Request

• Full-time Service Attendant-August (10-Mos) 2017.....$49,048
• Full-time Line Attendant-February (4-Mos) 2018.....$22,118
• Full-time Line Attendant-May (2-Mos) 2018.....$9,307
• Increase in Salaries for FY18 $83,218 if all goals are reached, 2019 $139,071 for these postions when fully staffed for one year.

 

 

Proposed City Council Motion:

I move to recommend to the City Council approval of Annual FY 2017-2018 Airport Budget

 

Background:

Staff will present the 2017-2018 Airport Budget to Board of Aeronautic Commissioners

 

Impact/Analysis:

Fuel expense expected to increase due to increase in traffic.

 

Presenter:

Presenter: John Ohrazda, Airport Manager

 

Recommendation:

Recommendation: Staff recommends to the City Manager that the proposed Airport Budget be included in their submission to City Council.

 

Committee Recommendation:

Committee Recommendation: BOAC recommends to the City Manager that the proposed Airport Budget be included in their submission to City Council.