Issue/Request:
Presentation: Capital Improvement Plan No-Tax Increase Bond Project Priorities (Transportation Projects)
Key Issues:
Discussion regarding the priority/sequencing of transportation projects funded by the April 2023 No-Tax Increase Bond in advance of Staff preparations for the 2025-2029 Capital Improvement Plan.
- The April 2023 No Tax Increase Bond Issue, approved by the voters, included several transportation projects totaling $98M.
- These projects were committed to the voters to begin within 10 years of the election.
- Review the projects, various project prioritization factors, and resources to set forth a reasonable expectation for delivery schedule/project sequencing.
Presenter
Michael Park, PE, Director of Public Works
Recommendation
As noted in the presentation and discussed at Public Works Committee.