File #: BILL NO. 18-97    Name:
Type: Ordinance Status: Agenda Ready
File created: 5/9/2018 In control: City Council - Regular Session
On agenda: 6/28/2018 Final action: 6/19/2018
Title: An ordinance authorizing an amendment to permit the extension of the project time period from December 31, 2017 to December 31, 2018 of the State Block Agreement by and between the City of Lee's Summit, Missouri, and the Missouri Highways and Transportation Commission, Granting State funds in the amount of $9,372,772.00 for rehabilitate and strengthen Runway 18-36, Extend Runway 18-36, Extend Runway 11-29; and Runway 18-36 and 11-29 lighting improvements. (BOAC 6-11-18) (PWC 6-19-18)
Attachments: 1. Ordinance, 2. Amendment to Agreement
Title
An ordinance authorizing an amendment to permit the extension of the project time period from December 31, 2017 to December 31, 2018 of the State Block Agreement by and between the City of Lee's Summit, Missouri, and the Missouri Highways and Transportation Commission, Granting State funds in the amount of $9,372,772.00 for rehabilitate and strengthen Runway 18-36, Extend Runway 18-36, Extend Runway 11-29; and Runway 18-36 and 11-29 lighting improvements. (BOAC 6-11-18) (PWC 6-19-18)


Body
Issue/Request:
An ordinance authorizing an amendment to permit the extension of the project time period from December 31, 2017 to December 31, 2018 of the State Block Agreement by and between the City of Lee's Summit, Missouri, and the Missouri Highways and Transportation Commission, Granting State funds in the amount of $9,372,772.00 for rehabilitate and strengthen Runway 18-36, Extend Runway 18-36, Extend Runway 11-29; and Runway 18-36 and 11-29 lighting improvements.

Key Issues:
· This request is a time extension to complete the project.
· This project includes rehabilitate and strengthen runway 18-36, Extend Runway 18-36, Extend Runway 11-29: and Runway 18-36 and 11-29 Lighting Improvements.
· This State Block grant is in the amount of $9,372,772, funding 90% of the cost of the construction and inspection for this project.
· Local matching funds of $520,710, 5% of the project cost were available from the Airport Construction Fund.
· An additional 5% of the project cost, $520,710, will come from a State Airport Aid Agreement.
· The extension will allow Lee’s Summit to receive the full grant amount.

Proposed City Council Motion:
First Motion: I move for a second reading of an ordinance authorizing an amendment to permit the extension of the project time period from December 31, 2017 to December 31, 2018 of the State Block Agreement by and between the City of Lee's Summit, Missouri, and the Missouri Highways and Transportation Commission, Granting State funds in t...

Click here for full text