Title
Presentation: Update on the Downtown Market Plaza and presentation of Guaranteed Maximum Price 1 (GMP 1).
Body
Issue/Request:
Key Issues:
This presentation will provide a general update on the progress with the Downtown Market Plaza Project as well as discuss the bidding process utilized for GMP 1. The following topics will be discussed:
- Recent Accomplishments
- Upcoming Milestones
- Project Sources and Uses
- GMP 1 - Early Civil Package Process
- Next Steps
- Current construction milestones
Presenter
Ryan A. Elam, P.E., Assistant City Manager