Body

Issue/Request:

Presentation: Harris Park Standpipe Demolition

 

Key Issues:

 

- The Harris Park Standpipe was constructed in 1960.
- The Harris Park Standpipe was removed from service in 2011 as it was no longer needed with the Hook, Scherer, and Ranson Towers.

- The 2023 Water Master Plan recommended demolition.

- The cost to recoat and maintain the Harris Park Standpipe is in excess of $2,000,000.

- The cost to demolish the Harris Park Standpipe is estimated to be $287,000.

- Water Utilities proposes to demolish the Standpipe and associated pump station in FY26.

 

Background:

The attached presentation will provide a brief history of the Harris Park Standpipe and summarize the reasons why Water Utilities supports the demolition of the facility.

 

Presenter

Amanda Bagwell, PE, Engineering Manager