Title
Public Hearing: First Amendment to the Discovery Park Tax Increment Financing Plan; Discovery Park Lee’s Summit, LLC, applicant
Body
Key Issues:
This is a public hearing to receive evidence, testimony and any public comments regarding the proposed First Amendment to the Discovery Park Tax Increment Financing Plan. The First Amendment (1) divides TIF Project 1 into TIF Projects 1A, 1B and 1C and (2) updates the TIF budget, project information, reimbursable projects costs and other key data to match the reality of the project today, as further detailed below.
Background:
The Discovery Park TIF Plan (“Original TIF Plan”) was approved through the adoption of Ordinance No. 9550 on November 15, 2022. The Discovery Park Tax Increment Financing Contract (the “TIF Contract”) to implement the Original TIF Plan was approved by Ordinance in July 2025 and was executed on July 25, 2023.
On October 1, 2026, the Developer under the TIF Contract filed the First Amendment to propose amendments to TIF Project 1 to divide that area into three separate TIF projects, which will allow the activation of TIF within these project areas on separate time schedules. The First Amendment also amends the project budget, the sources and uses and the cost benefit analysis to match the reality of the current project buildout.
A summary of the revisions to the key metrics of the plan under the First Amendment, as compared to the Original TIF Plan, are as follows:
· Total Project Costs decrease from about $951 million to about $901 million, which is about a 5.2% reduction.
· Maximum TIF reimbursement decreases from about $198.4 million to about $170.4 million, which is about a 14% reduction in TIF reimbursement. The total amount of TIF Reimbursement as a portion of total project costs is reduced from 20.9% to 18.9%.
· The maximum reimbursement from CID revenues decreases from about $10.9 million to about $5.9 million, which is a $5 million reduction.
· The maximum reimbursement from...
Click here for full text