Title
An Ordinance approving Change Order No. 2 to the agreement for the construction of Project No. 718 Sidewalk Gap Phase 2 with Phoenix Concrete, LLC for an increase in the contract price of $90,135.00, for a revised agreement amount of $666,617.48 and authorizing the City Manager to execute an agreement for the same. (PWC 6/8/26)
Body
Issue/Request:
An Ordinance approving Change Order No. 2 to the agreement for the construction of Project No. 718 Sidewalk Gap Phase 2 with Phoenix Concrete, LLC for an increase in the contract price of $90,135.00, for a revised agreement amount of $666,617.48 and authorizing the City Manager to execute an agreement for the same.
Key Issues:
· Pursuant to Ordinance 10238, the City and Phoenix Concrete, LLC (hereinafter "Contractor") entered into an Agreement for the construction of the Sidewalk Gap Phase 2, Project No.718, ("Base Agreement").
· The City and Contractor modified the Base Agreement, as amended, per Change Order No. 1 administratively in accordance with the City's Procurement Policy.
· The City desires to further modify the Base Agreement, as amended, due to added sections of sidewalk and additional costs associated with added work on Change Order No. 2 in order to complete the work.
Proposed City Council Motion:
FIRST MOTION: I move for adoption of Change Order No. 2 to the agreement for the construction of Project No. 718 Sidewalk Gap Phase 2 with Phoenix Concrete, LLC for an increase in the contract price of $90,135.00, for a revised agreement amount of $666,617.48 and authorizing the City Manager to execute an agreement for the same.
SECOND MOTION: I move for adoption of Change Order No. 2 to the agreement for the construction of Project No. 718 Sidewalk Gap Phase 2 with Phoenix Concrete, LLC for an increase in the contract price of $90,135.00, for a revised agreement amount of $666,617.48 and authorizing the City Manager to execute an agreement for the same.
Background:
The quantity (square feet) o...
Click here for full text