File #: SUBSTITUTE BILL NO. 16-141    Name:
Type: Other Business - Ordinance Status: Passed
File created: 6/3/2016 In control: City Council - Regular Session
On agenda: 7/7/2016 Final action: 7/7/2016
Title: AN ORDINANCE AWARDING BID NO. 14431683-C, CITY OF LEE'S SUMMIT WATER UTILITIES FACILITY TO FOGEL-ANDERSON CONSTRUCTION CO. IN THE AMOUNT OF $11,279,047.19 AND AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT FOR THE SAME.
Attachments: 1. Ordinance, 2. Bid Worksheet, 3. Agreement, 4. Recommendation of Award
Title
AN ORDINANCE AWARDING BID NO. 14431683-C, CITY OF LEE'S SUMMIT WATER UTILITIES FACILITY TO FOGEL-ANDERSON CONSTRUCTION CO. IN THE AMOUNT OF $11,279,047.19 AND AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT FOR THE SAME.

Body

Key Issues:
· HDR Engineering Inc. was awarded the design contract on January 29, 2014
· The final construction timeline is longer than was initially contracted for with HDR.
· The original contract did not include as-built drawings for the project.
· The original contract cost is $938,328 or 7.2% of the project cost
· The contract is currently $968,171 with Modification 1 or 7.4% of the project cost
· The cost of the proposed modification is $95,110 or 9.6% of the current design contract.
· If approved, design services will represent 8.2% of the project cost

Proposed Committee Motion:
I move to recommend to the City Council approval of AN ORDINANCE AWARDING BID NO. 14431683-C, CITY OF LEE'S SUMMIT WATER UTLILITIES FACILITY TO FOGEL-ANDERSON CONSTRUCTION CO. IN THE AMOUNT OF $11,279,047.19 AND AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT FOR THE SAME.

Background:
HDR engineering was selected and contract approved on January 29, 2014 for the design of the Water Utilities Facility. The project was bid on June 7, 2016 and the successful bidder’s contract is being brought forward parallel to this modification. This modification will add additional time for the construction oversight for this project to match the final construction documents. This modification will also cover the preparation of as-built drawings for the facility.






Impact/Analysis:

Funding Source Current Project Budget *Direct Expense Prior Encumbrances This Request Contract Remaining Balance
14431683 & 14431783 $14,000,000 $1,660,738 $ 203,498 $11,279,047.19 $856,717


Timeline:
This work will be performed over the construction contract duration of approximately 18 months.
Presenter
Jeff Thorn, Assistant Director of Engineering Services...