Title
AN ORDINANCE APPROVING CHANGE ORDER NO. 1 TO THE CONTRACT WITH B. DEAN CONSTRUCTION COMPANY FOR THE NORTHWEST QUADRANT T-HANGAR DEVELOPMENT PROJECT, AN INCREASE OF $395,084.44 FOR A REVISED CONTRACT PRICE OF $2,547,940.49. (PWC 3/20/18)
Body
Issue/Request:
AN ORDINANCE APPROVING CHANGE ORDER #1 TO THE CONTRACT WITH B. DEAN CONSTRUCTION COMPANY FOR THE NORTHWEST QUADRANT T-HANGAR DEVELOPMENT PROJECT, AN INCREASE OF $395,084.44 FOR A REVISED CONTRACT PRICE OF $2,547,940.49
Key Issues:
? Due to initial funding limitations, this project was split into two phases with the first phase being T-hangars constructed in FY 18 and the second phase, a taxiway to serve a protion of the hangars, constructed in FY 19.
? Based upon the current project schedule, Phase 1 should be completed in June or July 2018
? After consultation with the Finance Department regarding cash flow, it is possible to accelerate the construction of Phase 2.
? Since the paving unit prices have already been established by bid, Phase 2 can be added by change order and an additional seven T-hangar units will be available four to six months earlier than if the construction is done in two phases.
Proposed City Council Motion:
FIRST MOTION: I move for a second reading of AN ORDINANCE APPROVING CHANGE ORDER NO. 1 TO THE CONTRACT WITH B. DEAN CONSTRUCTION COMPANY FOR THE NORTHWEST QUADRANT T-HANGAR DEVELOPMENT PROJECT, AN INCREASE OF $395,084.44 FOR A REVISED CONTRACT PRICE OF $2,547,940.49.
SECOND MOTION: I move for adoption of AN ORDINANCE APPROVING CHANGE ORDER NO. 1 TO THE CONTRACT WITH B. DEAN CONSTRUCTION COMPANY FOR THE NORTHWEST QUADRANT T-HANGAR DEVELOPMENT PROJECT, AN INCREASE OF $395,084.44 FOR A REVISED CONTRACT PRICE OF $2,547,940.49.
Background
The Northwest Quadrant T-Hangar Development Project was to provide replacement hangars to some of the existing tenants being displaced as part of the Taxiway A project that de...