File #: BILL NO. 18-95    Name:
Type: Ordinance Status: Agenda Ready
File created: 5/2/2018 In control: City Council - Regular Session
On agenda: 6/28/2018 Final action: 6/19/2018
Title: An ordinance authorizing execution of Modification No. 3 to On-Call Agreement for Environmental Professional Engineering Services Yearly Contract with Stearns, Conrad and Schmidt, Consulting Engineers, Inc. DBA SCS Engineers (Original RFQ No. 2017-307, Renewal 2017-307/R1) for annual tasks associated with the Resource Recovery Park for a not to exceed cost of $76,200.00, and authorizing the City Manager to enter into an agreement for the same. (PWC 6-19-18)
Attachments: 1. Ordinance, 2. Landfill Agreement, 3. Attachment A 2019 Fee Schedule, 4. Original On-Call Agreement, 5. 2019 On-Call Renewal
Title
An ordinance authorizing execution of Modification No. 3 to On-Call Agreement for Environmental Professional Engineering Services Yearly Contract with Stearns, Conrad and Schmidt, Consulting Engineers, Inc. DBA SCS Engineers (Original RFQ No. 2017-307, Renewal 2017-307/R1) for annual tasks associated with the Resource Recovery Park for a not to exceed cost of $76,200.00, and authorizing the City Manager to enter into an agreement for the same. (PWC 6-19-18)

Body
Issue/Request:
An ordinance authorizing execution of Modification No. 3 to On-Call Agreement for Environmental Professional Engineering Services Yearly Contract with Stearns, Conrad and Schmidt, Consulting Engineers, Inc. DBA SCS Engineers (Original RFQ No. 2017-307, Renewal 2017-307/R1) for annual tasks associated with the Resource Recovery Park for a not to exceed cost of $76,200.00, and authorizing the City Manager to enter into an agreement for the same.

Key Issues:
-The City has entered into an On-Call Agreement with SCS Engineers to provide environmental professional engineering services (Renewal 2017-307/R1)
-The City is currently required to submit regular regulatory reports to the Missouri Department of Natural Resources (MDNR).
-The tasks specified in this Modification are required of the City for FY19 as owner of the Resource Recovery Park.

Proposed City Council Motion:
First Motion: I move for a second reading of an ordinance authorizing execution of Modification No. 3 to On-Call Agreement for Environmental Professional Engineering Services Yearly Contract with Stearns, Conrad and Schmidt, Consulting Engineers, Inc. DBA SCS Engineers (Original RFQ No. 2017-307, Renewal 2017-307/R1) for annual tasks associated with the Resource Recovery Park for a not to exceed cost of $76,200.00, and authorizing the City Manager to enter into an agreement for the same.

Second Motion: I move for adoption of an ordinance authorizing execution of Modification No. 3 to On-Call Agreement for Environ...

Click here for full text