Title
An Ordinance awarding the bid for Project No. 205 for the Bowlin Tank - Recoating Project to Cunningham Sandblasting & Painting Co. in the amount of $677,100.00, and authorizing the City Manager to execute an agreement for the same. (PWC 1/12/26)
Body
Issue/Request:
An Ordinance awarding the bid for Project No. 205 for the Bowlin Tank - Recoating Project to Cunningham Sandblasting & Painting Co. in the amount of $677,100.00, and authorizing the City Manager to execute an agreement for the same.
Key Issues:
· The project consists of recoating the interior, spot coating repairs to the exterior, and exterior grout replacement on Bowlin Tank. Bowlin Tank was last recoated and repaired in 2008.
· Project No. 205 is funded by the Water Equipment Replacement Fund for FY2026.
· Water Utilities issued a bid for Project No. 205 on November 5, 2025, in accordance with local policies and state statutes. Bids were opened on December 17, 2025.
· Cunningham Sandblasting & Painting Co. (hereinafter “Contractor”) was determined to be the lowest and best responsive and responsible bidder by City staff.
· The City and Contractor desire to enter into an agreement for Project No. 205.
Proposed City Council Motion:
FIRST MOTION: I move for second reading of an Ordinance awarding the bid for Project No. 205 for the Bowlin Tank - Recoating Project to Cunningham Sandblasting & Painting Co. in the amount of $677,100.00, and authorizing the City Manager to execute an agreement for the same.
SECOND MOTION: I move for adoption of an Ordinance awarding the bid for Project No. 205 for the Bowlin Tank - Recoating Project to Cunningham Sandblasting & Painting Co. in the amount of $677,100.00, and authorizing the City Manager to execute an agreement for the same.
Background:
Constructed in 1980, Bowlin Tank serves the north water distribution system as ground storage tank annually from June through October. Last recoated in 2008, the interior coating of the tank is beginn...