File #: BILL NO. 24-220    Name:
Type: Ordinance Status: Passed
File created: 11/19/2024 In control: City Council - Regular Session
On agenda: 12/9/2024 Final action: 12/17/2024
Title: An Ordinance approving and authorizing the execution of an amendment to the agreement between the City of Lee's Summit, Missouri and Titan Built, LLC to set Guaranteed Maximum Price 3 (GMP 3) for Joint Operations Facility and Police/Courts Phase 2 Renovations Project in the amount of $21,091,558.00, and authorizing the City Manager to execute the same. (PWC 12/9/24)
Sponsors: Public Works Admin & Engineering
Attachments: 1. Ordinance, 2. Exhibit A: Amendment to Agreement, 3. Supporting Document: Executed Agreement - Pre-Construction Services
Related files: BILL NO. 24-195, BILL NO. 24-150, BILL NO. 24-073

Title

An Ordinance approving and authorizing the execution of an amendment to the agreement between the City of Lee's Summit, Missouri and Titan Built, LLC to set Guaranteed Maximum Price 3 (GMP 3) for Joint Operations Facility and Police/Courts Phase 2 Renovations Project in the amount of $21,091,558.00, and authorizing the City Manager to execute the same. (PWC 12/9/24)

 

Body

Issue/Request:

An Ordinance approving and authorizing the execution of an amendment to the Agreement between the City of Lee's Summit, Missouri and Titan Built, LLC to set Guaranteed Maximum Price 3 (GMP 3) for Joint Operations Facility and Police/Courts Phase 2 Renovations Project in the amount of $21,091,558.00, and authorizing the City Manager to execute the same.

 

 Key Issues:

 

                     Pursuant to Ordinance No. 9898 approved on April 23, 2024, the City entered into a preconstruction services agreement (Agreement) with Titan Built, LLC for certain preconstruction services and to establish a guaranteed maximum price (“GMP”) to construct the Joint Operations Facility and Phase 2 Police/Courts Renovations. 

                     City Council approved an amendment for GMP 1, addressing long-lead items for the Police/Courts Phase 2 Renovations Project work in September of 2024.

                     City Council approved an amendment for GMP 2, addressing site, foundation, and structural work for the Joint Operations Facility Project in October of 2024.

                     For GMP 3, addressing exterior and interior construction for the Joint Operations Facility and additions and parking lot improvements for the Police/Courts Phase 2 Renovations Project, Titan Built LLC received 123  bids and will award 30 subcontracts.

                     City staff supports amending the current Agreement with Titan Built for GMP 3 in the amount of $21,091,558.00.

 

Proposed Committee Motion:

I move to recommend to City Council approval of the Ordinance approving and authorizing the execution of an amendment to the Agreement between the City of Lee's Summit, Missouri and Titan Built, LLC to set Guaranteed Maximum Price 3 (GMP 3) for Joint Operations Facility and Police/Courts Phase 2 Renovations Project in the amount of $21,091,558.00, and authorizing the City Manager to execute the same.

 

Proposed Council Motion:

FIRST MOTION: I move for second reading of an Ordinance approving and authorizing the execution of an amendment to the Agreement between the City of Lee's Summit, Missouri and Titan Built, LLC to set Guaranteed Maximum Price 3 (GMP 3) for Joint Operations Facility and Police/Courts Phase 2 Renovations Project in the amount of $21,091,558.00, and authorizing the City Manager to execute the same.

 

 

SECOND MOTION: I move for adoption of an Ordinance approving and authorizing the execution of an amendment to the Agreement between the City of Lee's Summit, Missouri and Titan Built, LLC to set Guaranteed Maximum Price 3 (GMP 3) for Joint Operations Facility and Police/Courts Phase 2 Renovations Project in the amount of $21,091,558.00, and authorizing the City Manager to execute the same.

 

Background:

In 2023, voters approved a No Tax Increase Bond for public safety and emergency preparedness projects, including the Joint Operations Facility and Phase 2 Police/Courts Renovations. On December 19, 2023, the City Council passed Ordinance No. 9886 recommending approval of a contract between the City and Hoefer Welker for the architectural work associated with the Joint Operations Facility and Phase 2 Police/Courts Renovations. 

 In November 2023, the City issued RFQ 2024-043 for Pre-Construction Services and Construction Manager at Risk to identify qualified companies which could construct the projects as a Construction Manager at Risk. Eight firms responded to the RFQ. A selection committee comprised of representatives from the City, Police Department, and Fire Department held interviews with selected firms in December 2023.  Titan Built, LLC was selected as the most qualified respondent. On April 23, 2024 the City Council approved Ordinance No. 9898, which authorized the City to enter into a Pre-Construction Agreement with Titan Built, LLC.

On September 24, 2024 the City Council approved Ordinance No. 24-150, which authorized an amendment for GMP 1. On October 25, 2024, the City Council approved Ordinance 24-195, which authorized an amendment for GMP 2.

GMP 1, GMP 2 and GMP 3 (as proposed) totals $29,568,000 for the Joint Operations Facility and Phase 2 Police/Courts Renovations.  This total amount, for the construction of these two projects, is within the Capital Improvement Plan authorized remaining budget for the two facilities projects (and associated specific line items) committed to voters in the NTIB initiative.

 

Impact/Analysis:

GMP 3 will allow the Construction Manager to construct the exterior shell and interior finishes of the Joint Operations Facility and built additions for and improve parking lots for the Police/Courts Phase 2 Renovations Project.

 

Project Timeline:

Start: August 2024

Completion: March 2026

 

Presenter

Sharon Bloom, Project Manager

 

Recommendation

City staff recommends approval.

 

Committee Recommendation 

Committee Recommendation: The Public Works Committee voted unanimously 3-0 (Vice Chair Prier "Absent"), to recommend to City Council approval of an Ordinance approving and authorizing the execution of an amendment to the Agreement between the City of Lee's Summit, Missouri and Titan Built, LLC to set Guaranteed Maximum Price 3 (GMP 3) for Joint Operations Facility and Police/Courts Phase 2 Renovations Project in the amount of $21,091,558.00, and authorizing the City Manager to execute the same.