File #: 2025-6706    Name:
Type: Public Hearing - Sworn Status: Agenda Ready
File created: 1/8/2025 In control: City Council - Regular Session
On agenda: 2/25/2025 Final action:
Title: Public Hearing: Application #PL2024-283 - Rezoning from AG to CP-2 and Preliminary Development Plan - View High Sports Complex, 3350 NW Ashurst Drive; Engineering Solutions, LLC, applicant. (Note: This item was continued from February 25, 2025 per staff's request.)
Attachments: 1. 1-23-2025 PC Action Letter, 2. Staff Presentation, 3. Staff Letter, 4. Transportation Impact Analysis, 5. Rezoning Exhibit, 6. Preliminary Development Plan and Architectural Elevations, 7. Storm Water Memorandum, 8. Traffic Impact Study, 9. Parking Determination Memorandum, 10. Modification Request Letter, 11. Neighborhood Meeting Minutes, 12. Email from The Summit Church, 13. Location Map

Title

Public Hearing: Application #PL2024-283 - Rezoning from AG to CP-2 and Preliminary Development Plan - View High Sports Complex, 3350 NW Ashurst Drive; Engineering Solutions, LLC, applicant.

(Note: This item was continued from February 25, 2025 per staff's request.)

 

Body

Issue/Request:

The applicant proposes a rezoning from AG to CP-2 and preliminary development plan (PDP) for a 164,081 sq. ft. building to house a sports complex consisting of one indoor soccer field and six indoor basketball courts or twelve volleyball courts.  The site will also house one outdoor soccer field and five outdoor pickleball courts. The proposed building is a single-story structure with a mix of materials that includes translucent panels, glass, and metal panels.  The project site is composed of one parcel that has The Summit Church in the northeastern corner.  The entire property is currently zoned AG (Agricultural) and the applicant is proposing to rezone 15.40 acres to CP-2 (Planned Community Commercial) to accommodate the use. The rezoning will also cover a future 2-acre parcel for commercial development which is being shown as conceptual. At the time of development, that commercial site will require a Preliminary Development Plan and a Final Development Plan.

The applicant is requesting two (2) modifications; a modification to the high impact buffer requirement along the southern and eastern property lines and a modification to the allowable percentage of metal on the building façade.

 

Presenter

Matt Schlicht, PE, Applicant Representative

Adair Bright, AICP, Senior Planner

 

Recommendation

Recommendation: With the conditions of approval below, the application meets the recommendations of the Ignite! Comprehensive Plan and requirements of the UDO.

 

    1. Development shall be in accordance with the preliminary development plan with an upload date of January 3, 2025.

    2. A modification shall be granted to UDO Sec. 8.170.A to allow for architectural metal panels on more than 40% of all facades as depicted on the plan set uploaded on January 3, 2025.

    3. A modification shall be granted to UDO Sec. 8.900.A to waive the requirement for a six-foot high masonry wall, opaque vinyl fence, or three-foot high berm within the southern and eastern buffer yards.

     4. A copy of the Shared Parking Agreement shall be provided to staff prior to approval of the Final Development Plan.

     5. Road improvements shall be constructed as recommended in the Transportation Impact Analysis conducted by staff dated January 6, 2025.

 

Committee Recommendation

Committee Recommendation: A motion was made by Board Member Frazier, seconded by Board Member Jana-Ford, that this application be approved. The motion carried unanimously.