Skip to main content
File #: TMP-3368    Name:
Type: Ordinance Status: Agenda Ready
File created: 6/10/2025 In control: Public Works Committee
On agenda: 8/11/2025 Final action:
Title: An Ordinance awarding the bid for Project No. 718 for the Sidewalk Gap Project Phase 2 to Myers Construction and Landscaping, LLC. in the amount of $279,567.50, and authorizing the City Manager to execute an agreement for the same.
Sponsors: Public Works Admin & Engineering
Attachments: 1. Ordinance, 2. Exhibit A: Agreement, 3. Supporting Document: Bid Tab, 4. Supporting Document: Project Map
Related files: 2025-6751
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

An Ordinance awarding the bid for Project No. 718 for the Sidewalk Gap Project Phase 2 to Myers Construction and Landscaping, LLC. in the amount of $279,567.50, and authorizing the City Manager to execute an agreement for the same.

 

Body

Issue/Request:

An Ordinance awarding the bid for Project No. 718 for the Sidewalk Gap Project Phase 2 to Myers Construction and Landscaping, LLC. in the amount of $279,567.50, and authorizing the City Manager to execute an agreement for the same.

 

 

Key Issues:

  The Sidewalk Gap Project Phase 2 (hereinafter "Project") will install approximately 15,925 square feet of new sidewalk where sidewalk gaps currently exist, install or replace about 18 sidewalk ramps for sidewalk accessibility and to comply with the current applicable Americans with Disability Act (A.D.A.) standards, and remove and replace an estimated 9620 square feet of driveways to comply with A.D.A. standards where impacted by the connected pedestrian route.

  Sites were determined based on the sidewalk gap prioritization guidance given by City Council for the Sidewalk Gap Program.

•  Public Works Engineering issued an advertisement for bids for the construction of the Project on July 10, 2025, guided by local policies and state statutes. 

•  Myers Construction and Landscaping, LLC. (hereinafter "Contractor") was determined to be the lowest and best bidder by City staff.

The City desires to enter into an agreement with the Contractor to construct the Project.

                     

Proposed City Council Motion:

FIRST MOTION: I move for second reading an Ordinance awarding the bid for Project No. 718 for the Sidewalk Gap Project Phase 2 to Myers Construction and Landscaping, LLC. in the amount of $279,567.50, and authorizing the City Manager to execute an agreement for the same.

 

 

SECOND MOTION: I move for adoption of an Ordinance awarding the bid for Project No. 718 for the Sidewalk Gap Project Phase 2 to Myers Construction and Landscaping, LLC. in the amount of $279,567.50, and authorizing the City Manager to execute an agreement for the same.

 

 

Background:

This program intends to incrementally address gaps in the sidewalk network in support of the Ignite! Strategic Plan, Ignite! Comprehensive Plan, Livable Streets Policy and current sidewalk standards for improved non-motorized transportation, safety, accessibility and quality of life. Sidewalk gaps resulted throughout the community from a variety of reasons related to new development work and capital improvements that either did not require sidewalk at that time or were granted waivers to required sidewalk. Recent changes to development construction standards now require sidewalks and curb ramps be installed along all streets to minimize the propagation of more sidewalk gaps in the future.  Historically, sidewalk construction was not required or tied to building construction. Some reasons for sidewalk gaps include previous standards that did not require sidewalks, waivers to development standards at developer’s request, unmitigated topographic challenges, common tracts between subdivision boundaries, or individual parcels that historically remained undeveloped within a long-developed subdivision. 

 

Sidewalks, especially the closure of sidewalk gaps, are an increasing public demand.  The Sidewalk Gap Program is principally funded by the ½-cent 2017 CIP Sales Tax Renewal approved by voters.  Additional sidewalk gap funding was authorized in the April 2023 No Tax Increase Bond Issue.  Guidance was given by City Council to prioritize sites with an emphasis on Use/Demand and Safety.  Building upon a prior Sidewalk Inventory and Gap Study, the prioritization of sidewalk locations relies upon a multi-tiered and multi-factored system of influential criteria focused on Use/Demand (e.g. pedestrian activity) and Safety (e.g. schoolchild presence, risk exposures like traffic speed and volume, etc.).  Sites were selected based on this priority guidance; which is referenced in the associated packets linked to this presentation.  These sites were visually evaluated by an engineer to assess the level of difficulty for construction as another benefit/cost measure for prioritization of limited funds.  Phase 2 of the program will address gaps with more engineering required due to grade changes and additional driveway work than was necessary for Phase 1 and should address a majority of the remaining Tier 1, highest priority gaps as established by council.  There will still be a lot of priority sidewalk gaps remaining after this initial phase and following the expenditure of all identified program funds.  There is an inventory of sidewalk gaps exceeding $50 Million throughout the City.  Phase 2 will not expend the balance of funds for sidewalk gaps.  Phase 3 will continue to address gaps and areas with more challenging engineering, utility relocation or property acquisition over the next year(s).  An annual review and update on the sidewalk gap program is typically provided to the Public Works Committee after each new year. 

 

 

Impact/Analysis:

This project is expected to close remnant gaps and will help to increase non-motorized mobility and safety within neighborhoods throughout the City.

 

Timeline:

 

Other Information/Unique Characteristics:

 

Presenter

Erin Ralovo, Senior Staff Engineer

 

Recommendation

Staff recommends approval.

 

Committee Recommendation

Committee Recommendation: [Enter Committee Recommendation text here]